Solving capacity problems

Solving capacity problems
The schedule view uses a calendar and colour codes to show you who is at capacity, and when.  The schedule is on your dashboard. At the top of your scre...
Tue, 10 Mar, 2020 at 11:12 AM
Extending the deadline
If the deadline is flexible, you could solve this problem by changing the deadline, and having the project finish later. This means he’s spending less time ...
Fri, 20 Mar, 2020 at 11:31 AM
Giving the task to someone else
If extending the deadline is not an option, you can take the entire job off Aurif, and give it to someone who has capacity to do it.  If we look at the ...
Fri, 20 Mar, 2020 at 11:32 AM
Splitting a task between staff members
Splitting a job between staff members is another way to handle this problem. 80 hours over the next couple weeks may put Aurif over capacity, but he probabl...
Fri, 20 Mar, 2020 at 11:32 AM